>> Location: Assiut- Egypt
Scope of work
>> Dismantling of old MCCs
>> Dismantling existing cables from the filter
>> Remove lighting and reinstallation of bag filters
>> Supply and install cable tray
>> Making necessary joint for shortage power cables
>> Rerouting from outgoing cable feed of MCC3 to spare feeder in LS panel
>> Supply, pull and connect new interface cables
>> Supply and install new MCCs for bag filters and conditioning tower
>> Supply, pull and connect new LCB cables between junction boxes under station and MCCs
>> Supply new junction box for LCBs under the station for the bag filters motor
>> Set (1 and 2) junction box and new PLC I/O panel for transformer signals
>> Modifications in TAC panels, adding new signals
>> Modifications in PLC and ECS, adding new signals
>> Supply, pull and connect power and control cables
>> Supply and install digital junction box
>> Supply and install analogue junction box
>> Supply and install new pipes and support
>> Supply and install box with transmitter for thermocouples
>> Supply new earthing cables for filter
>> Modificationsin TAC Panels, adding new signal related to bag