Scope of work
>> Dismantling old cables, cable routings, distribution panels, electrical drives and all accessories under line 3 rehabilitation scope
>> Installing new equipment for line 3 process in different sections
>> Erection of new electrical lighting AC and emergency DC system works for the electrical room, transformer room, and outdoor lighting system
>> Erection of new fire alarm system works for the electrical rooms, transformer room, and CCR
>> Installation of MCCs for various plant areas
>> Earthing system installation including earthing cables, concrete pit, earthing copper rod and testing bus bar
>> Medium voltage cables erection and terminations
>> Final check, tests, and commissioning